Microgrid & Energy Storage · Engineered in Shenzhen
Solution

Off-Grid Microgrid for Islands and Remote Sites

PV, battery and diesel on one AC bus — 72% less diesel on our 2 MW / 4 MWh reference site.

PV + BESS + DieselIsland / remoteDiesel cut 72%
200 kW – 2 MWTypical scale

An island or a remote mine has the same problem in different clothes: fuel arrives by boat or truck, the genset runs at a poor load factor, and the cost per kWh is set by logistics rather than by generation. The fix is not a bigger battery — it is running the diesel only when the battery and the sun cannot carry the load.

The architecture

PV feeds a DC bus through MPPT modules. A bidirectional PCS couples that bus to the island AC network, and the battery sits on the same bus through DC/DC converters. The genset stays, but the EMS decides when it runs: above a state-of-charge floor the diesel is stopped entirely, and it restarts only when the battery cannot cover the evening peak or when a large load steps in.

What decides the sizing

  • Night load sets the battery, not the daily energy. A site using 4 MWh a day but 2.5 MWh between sunset and sunrise needs a battery sized to the night, not the day.
  • Genset minimum load sets the floor. Below roughly 40% load a diesel set fouls; the EMS therefore runs it at a working load and dumps surplus into the battery rather than idling.
  • PV oversizing is cheaper than battery oversizing when the load is daytime-heavy. DC-coupled MPPT lets one array charge the battery and serve load simultaneously.

What we delivered

On a 2 MW / 4 MWh island system, the diesel share fell 72%, the levelised cost dropped from $0.42 to $0.21 per kWh, and measured availability reached 99.3%. Payback was 4.2 years at local fuel prices. The genset was not removed — it was demoted from prime power to backup, which is what made the payback defensible.

System outline

What goes on site.

Generation
PV arraySized to daytime load plus battery recharge, DC-coupled through MPPT modules
BatteryLiFePO4 cabinets, 241–522 kWh per unit, parallel banks
Diesel gensetRetained as backup, absorbed into the EMS as a controllable source
Conversion
PCSBidirectional, 125–500 kVA per unit, up to 3 units parallel
MPPT60 or 120 kW modules, 1 or 4 channels each
TransferSTS with 0 ms active transfer, <10 ms passive
Control
EMSSOC balancing, PV prioritisation, genset start/stop, load shedding
MonitoringCloud platform with remote alarm and monthly reporting
Reference outcome
Diesel consumption−72% against the pre-project baseline
Payback4.2 years
Availability99.3% measured uptime
Cost of energy$0.42 → $0.21 per kWh
CO₂ avoided≈1,052 t per year
Related

Other architectures

250 kVA – 1.5 MVA
PV + Storage + Diesel Hybrid for Commercial Sites
One cabinet holds the PCS, MPPT, EMS and transfer switch — grid-tied, with the diesel absorbed into the control logic.
105 kW – 250 kW · 241 – 522 kWh
Containerised C&I Storage for Peak Shaving
Liquid-cooled cabinets from 105 kW / 241 kWh, paralleled to 250 kW / 522 kWh for demand-charge reduction.